Rule 5
Application To Be Submitted To Obtain A License To Conduct A Survey Of Transmission Of Electricity
-
Any person or corporate body who is  interested to conduct a survey of transmission of electricity shall have to  submit an application in triplicate stating the following particulars relating to
the electricity transmission project to the Secretary through the Electricity  Development Department in the format as prescribed in Schedule-3:-
(a) Preliminary route-map of electricity transmission line (proposed main  transmission line and alternative line also should be shown),
(b) Necessity, purpose and total length of the transmission line,
(c) Standard and capacity of voltage to be used for transmission,
(d) If the electricity is to be supplied at once Maximum load of electricity
and types of consumers,
(e) Estimated amount of cost and time for the completion of transmission
line (both the survey and construction),
(f) Other necessary matters.